Retrofitting of noise barriers on Tuen Mun Road (Town Centre Section)
Project Description:
To mitigate the noise impact of Tuen Mun Road on neighbouring residents by retrofitting noise barriers and enclosures
Retrofitting of noise barriers and enclosures of about 800metres (m) long on Tuen Mun Road between Rose Dale Garden and Lakeshore Building.
Estimated Project Cost
HK$826.5 Million
Construction Commencement Date:
Dec 2015
Commissioning Date: