Improvement works at Tsuen Tsing Interchange
Project Description:
The objective of the proposed works is to improve the traffic condition at Tsuen Tsing Interchange. The scope of works mainly comprises provision of an exclusive left-turn lane from Tsuen Wan Road (Tuen Mun bound) to Tsing Yi, extension of existing vehicular bridge at Texaco Road and other improvement works for Tsuen Tsing Interchange.
More information can be found in the project website.
Estimated Project Cost: :
HK$ 581.4 Million
Construction Commencement Date:
April 2024
Anticipated Commissioning Date:
2027
Contract(s):
Contract No. HY/2022/18
Scope | Construction of a traffic lane to allow exclusive left-turning traffic movement from the down ramp of Tsuen Wan Road westbound (Tuen Mun bound) to Tsing Tsuen Road (Tsing Yi bound), construction of a single-lane vehicular bridge at Texaco Road (westbound) to connect to an existing vehicular bridge section above Tsuen Tsign Interchange which has yet to be opened to traffic, widening part of the roundabout at Tsuen Tsing Interchange and improving its junction, and other associated works. |
Commencement Date | April 2024 |
Anticipated Completion Date |
2027 |
Contract Sum | HK$ 360.65 Million |
Contractor | Lanon - Sinohydro Joint Venture |
Resident Engineer | AECOM Asia Company Limited |
Consultant:
AECOM Asia Company Limited