Flyover from Kwai Tsing Interchange Upramp to Kwai Chung Road
Project Description:
The objective of the proposed works is to relieve the traffic congestion at the Kwai Tsing Interchange Upramp. The scope of works mainly comprises the construction of a single-lane vehicular bridge connecting Tsuen Wan Road southbound fast lane to Kwai Chung Road, widening of a section of Tsuen Wan Road southbound traffic lane between Kwai Tsing Interchange upramp and Kwai Chung Road, and other ancillary works.
Estimated Project Cost:
HK$472.0 Million
Construction Commencement Date:
June 2021
Anticipated Commissioning Date:
Mid-2025
Contract(s) :
Contract No. HY/2020/08
Scope | To construct a single-lane vehicular bridge connecting Tsuen Wan Road southbound fast lane of Kwai Chung Road and widen a section of Tsuen Wan Road southbound traffic lane between Kwai Tsing Interchange upramp and Kwai Chung Road. |
Commencement Date | June 2021 |
Anticipated Completion Date | Mid-2025 |
Contract Sum | HK$306.6 Miliion |
Contractor | Peako Engineering Co. Limited |
Resident Engineer | WSP (Asia) Limited |