Lift and Pedestrian Walkway System between Saddle Ridge Garden and Sai Sha Road
Project Description:
The proposed "Lift and Pedestrian Walkway System between Saddle Ridge Garden and Sai Sha Road" is a "Hillside Escalator Link and Elevator System". The Project aims to improve the accessibility of the residential areas, the community facilities and the transport facilities between the uphill areas and Ma On Shan town centre. It will provide a comfortable, convenient, safe and barrier-free pedestrian access to the public (in particular the elderly and the disabled).
Estimated Project Cost: :
HK$141.1 Million
Construction Commencement Date:
October 2022
Anticipated Commissioning Date:
4th quarter of 2025
Contract(s):
Contract No. HY/2022/07
Scope |
|
Commencement Date |
October 2022 |
Anticipated Completion Date | Q4 2025 |
Contract Sum | HK$98.66 Million |
Contractor | Wing Hing Construction Company Limited |
Resident Engineer | Mannings (Asia) Consultants Limited |
Consultant:
Mannings (Asia) Consultants Limited