New Wang Tong River Bridge

Project Description:

To construct a new bridge to replace the existing Wang Tong River Bridge in Mui Wo to enhance road safety by widening the river crossing and segregating pedestrians from cyclists.

Estimated Project Cost:

HK$99.7 Million

Construction Commencement Date :

9/2020

Completion Date

Main works completed on 28 March 2024 and remaining works are in progress.

Contract(s):

Contract No. HY/2019/14

Scope To construct a twin-bridge comprising a footbridge and a cycle bridge across Wang Tong River in Mui Wo, and to demolish the existing Wang Tong River Bridge
Commencement Date September 2020
Completion Date Main works completed on 28 March 2024 and remaining works are in progress.
Contract Sum HK$78.8 Million
Contractor Unison Construction Engineering Limited
Resident Engineer Works Division of Highways Department

 

Consultant:

Nil